Home » TRAC Capability – Former BHS / Co-op Building
Albion Street, Hull, HU13TF
Asbestos Consultancy, Air Monitoring and Survey requirements to facilitate the demolition of the building on completion of works.
TRAC began the project for Vinci in October 2020 after compiling a large, comprehensive demolition survey and creating the scope of works for removals after the completion of the 1st phase of asbestos removal works from the building.
On appointment of the LARC (Licensed Asbestos Removal Contractor), environmental cleaning was instructed throughout the building to allow safe access to all floors without control factors.
TRAC provided further surveys to supplement information collated from the original survey to detail extent of contamination to areas returning positive samples or to areas like internal walls which could be removed as part of the soft strip.
Non-licensed and licensed products were found throughout the building, items such as bitumen and textured coatings which could be removed under controlled conditions. AIB (Asbestos insulating board) and thermal insulation are licensable products and require removal under fully controlled conditions. This required the construction of an enclosure which is generally constructed with timber and 1000 gauge polythene sheeting and must be fully sealed, include an Airlock & Baglock (where possible) CCTV and/or vision panels and Negative Pressure Units to allow for filtering the air within the enclosure. A Decontamination Unit must be present on site for these works to allow operatives to decontaminate after exiting the enclosure. When removal works have been completed by the LARC, they will hand over the enclosure to the Analyst for a 4-stage clearance inspection.
During our time on site TRAC has completed 29 4SC inspections to allow for reoccupation into the cleaned areas.
TRAC has liaised with principal contractor Vinci Construction. completing Surveys on request, daily air monitoring, facilitating land remediation and WAC (Waste Acceptance Criteria) samples for the groundworks of a new Community Diagnostics Centre building to be constructed on site, ensuring all parties were providing an effective, coordinated service.
Bespoke scaffolding was required to enable the removal of Durasteel panels and Thermal Insulation residues identified in TRAC Demolition survey, Basement to 4th floor. This was constructed within the lift shaft which was split in the middle by Durasteel panels. Nuts and bolts could then be removed from the lift shaft frame allowing for safe removal of the panels with minimal damage. Thermal insulation residues could then be thoroughly cleaned from the metal framework throughout.
Insufficient hand tools for removal of concrete infills from within block ceiling:
After unsuccessful attempts to remove concrete infills from the block ceiling it was determined that a BROKK would be far more efficient to remove the infills. This remote-controlled machine can be controlled from a safe distance and was able to remove the infills effectively in a fraction of the time. It could also be dismantled and fully decontaminated before the enclosure was removed.
Access to Lift shaft
Insufficient hand tools
Bespoke scaffolding throughout lift shaft.
BROKK to facilitate safe and efficient removal of concrete infills.
The project outcome aimed to hand the client a building ready for structural demolition on the completion of removal works.
This will allow for regeneration in the area whilst retaining some local heritage with the original Three Ships Mural being retained for any future developments.
With the construction of the new Community Diagnostic Centre by Vinci Construction the future is looking bright for the area.
Suite 5
The Pavilions
Bridge Hall Drive
Bury BL9 7NX
Hexagon House
64 Walton Road
East Molesey
Surrey KT8 0DL